the upgrading of the dry mill with a new moulder and more effective timber handling equipment; and
4 the upgrading of the dry mill with a new moulder and more effective timber handling equipment; and
5. the installation of a new high temperature kiln and reconditioner to meet the increased capacity.
Third Stage
This will increase annual log input capacity by 50,000 m3 up to 250,000 m3, and will be completed in 1996/97. The Third Stage will involve upgrades to the debarker/sorting line, and a modernising of the original high temperature kiln.
Fourth Stage
This will increase annual log input capacity by 50,000 m3 up to 300,000 m3, and will be completed in 1998/99. The Fourth Stage will involve: —
1. the installation in the green mill of a curve canter/gang saw and a two saw edger optimiser;
2. an increase in log handling plant capacity;
3. the establishment of a remanufacturing section;