(1) Subject to the EP Act, in respect of each proposal submitted pursuant to subclause (1) of Clause 5 the Minister shall —
6 (1) Subject to the EP Act, in respect of each proposal submitted pursuant to subclause (1) of Clause 5 the Minister shall —
approve of the proposal without qualification or reservation; or
defer consideration of or decision upon the same until such time as the Company submits a further proposal or proposals in respect of some other of the matters mentioned in subclause (1) of Clause 5 not covered by the said proposal as shall be specified by the Minister; or
require as a condition precedent to the giving of his approval to the said proposal that the Company make such alteration thereto or comply with such conditions in respect thereto as he thinks reasonable and in such a case the Minister shall disclose his reasons for such conditions,
PROVIDED ALWAYS that where implementation of any proposals hereunder has been approved pursuant to the EP Act subject to conditions or procedures, any approval or decision of the Minister under this Clause shall if the case so requires incorporate a requirement that the Company make such alterations to the proposals as may be necessary to make them accord with those conditions or procedures.
Advice of Minister’s decision
The Minister shall within 2 months after receipt of proposals pursuant to subclause (1) of Clause 5 or where the proposals are to be assessed under section 40(1)(b) of the EP Act then within two months after service on him of an authority under section 45(7) of the EP Act give notice to the Company of his decision in respect to the proposals.
Consultation with Minister
If the decision of the Minister is as mentioned in either of paragraphs (b) or (c) of subclause (1) the Minister shall afford the Company full opportunity to consult with him and should it so desire to submit new or revised proposals either generally or in respect to some particular matter.
Minister’s decision subject to arbitration
If the decision of the Minister is as mentioned in either of paragraphs (b) or (c) of subclause (1) and the Company considers that the decision is unreasonable the Company within two months after receipt of the notice mentioned in subclause (2) may elect to refer to arbitration in the manner hereinafter provided the question of the reasonableness of the decision PROVIDED THAT any requirement of the Minister pursuant to the proviso to subclause (1) shall not be referable to arbitration hereunder.
Arbitration award
An award made on an arbitration pursuant to subclause (4) shall have force and effect as follows —
if by the award the dispute is decided against the Company then unless the Company within 3 months after delivery of the award gives notice to the Minister of its acceptance of the award this Agreement shall on the expiration of that period of 3 months cease and determine; or
if by the award the dispute is decided in favour of the Company the decision shall take effect as a notice by the Minister that he is so satisfied with and approves the matter or matters the subject of the arbitration.
Effect of non‑approval of proposals
Notwithstanding that under subclause (1) any proposals of the Company are approved by the Minister or determined by arbitration award, unless each and every such proposal and matter is so approved or determined by 30 September 1993 or by such extended date or period if any as the Company shall be granted pursuant to the provisions of this Agreement then the Minister may give to the Company 12 months notice of intention to determine this Agreement and unless before the expiration of the said 12 months period all the detailed proposals and matters are so approved or determined this Agreement shall cease and determine subject however to the provisions of Clause 24.
Implementation of proposals
Subject to and in accordance with the EP Act and any approvals and licences required under that Act the Company shall implement the approved proposals in accordance with the terms thereof.
Additional proposals
7. (1) If the Company at any time during the continuance of this Agreement desires to significantly modify expand or otherwise vary its activities at the pine log sawmill carried on pursuant to this Agreement beyond those activities specified in any approved proposals it shall give notice of such desire to the Minister and within 2 months thereafter shall submit to the Minister detailed proposals in respect of all matters covered by such notice and such of the other matters mentioned in paragraphs (a) to (g) of subclause (1) of Clause 5 as the Minister may require.
The provisions of Clause 5 and Clause 6 (other than subclauses (5) and (6) of Clause 6) shall mutatis mutandis apply to detailed proposals submitted pursuant to this subclause with the proviso that the Company may withdraw such proposals at any time before approval thereof or, where any decision of the Minister in respect thereof is referred to arbitration,within 3 months after the award by notice to the Minister that it shall not be proceeding with the same. Subject to and in accordance with the EP Act and any approvals and licences required under that Act the Company shall implement approved proposals pursuant to this Clause in accordance with the terms thereof.
Protection and management of the environment
8. (1) The Company shall in respect of the matters referred to in paragraph (g) of subclause (1) of Clause 5 and which are the subject of approved proposals, carry out a continuous programme including monitoring to ascertain the effectiveness of the measures it is taking pursuant to such approved proposals for the protection and management of the environment and shall as and when reasonably required by the Minister from time to time submit to the Minister a detailed report thereon.
Whenever as a result of its activities pursuant to subclause (1) or otherwise information becomes available to the Company which in order to more effectively protect or manage the environment may necessitate or could require any changes or additions to any approved proposals or require matters not addressed in any such proposals to be addressed the Company shall forthwith notify the Minister thereof and with such notification shall submit a detailed report thereon.
The Minister may within 2 months of the receipt of a detailed report pursuant to subclause (1) or (2) notify the Company that he requires additional detailed proposals to be submitted in respect of all or any of the matters the subject of the report and such other reasonable matters as the Minister may require in connection therewith.
The Company shall within 2 months of receipt of a notice given pursuant to subclause (3) submit to the Minister additional detailed proposals as required and the provisions of subclauses (1), (2), (3) and (4) of Clause 6 shall mutatis mutandis apply.
Subject to and in accordance with the EP Act and any approvals and licences required under that Act the Company shall implement the decision of the Minister or an award on arbitration as the case may be in accordance with the terms thereof.
Use of local labour professional services and materials