s 23

(1) In any of the following events namely if —

In force

23 (1) In any of the following events namely if —

(a)

(i) the Company makes default which the State considers material in the due performance or observance of any of the covenants or obligations of the Company in this Agreement; or

(ii)

the Company abandons or repudiates this Agreement or its activities under this Agreement

and such default is not remedied or such activities resumed within a period of 180 days after notice is given by the State as provided in subclause (2) or, if the default or abandonment is referred to arbitration, then within the period mentioned in subclause (3); or

(b)

the Company goes into liquidation (other than a voluntary liquidation for the purpose of reconstruction) and unless within 3 months from the date of such liquidation the interest of the Company is assigned to an assignee approved by the Minister under Clause 19

the State may by notice to the Company determine this Agreement.

(2)

The notice to be given by the State to the Company in terms of paragraph (a) of subclause (1) shall specify the nature of the default or other ground so entitling the State to exercise such right of determination.

(3)

(a) If the Company contests the alleged default abandonment or repudiation referred to in paragraph (a) of subclause (1) the Company shall within 60 days after notice given by the State as provided in subclause (2) refer the matter in dispute to arbitration.

(b)

If the question is decided against the Company, the Company shall comply with the arbitration award within a reasonable time to be fixed by that award PROVIDED THAT if the arbitrator finds that there was a bona fide dispute and that the Company was not dilatory in pursuing the arbitration, the time for compliance with the arbitration award shall not be less than 90 days from the date of such award.

(4)

If the default referred to in paragraph (a) of subclause (1) shall not have been remedied after receipt of the notice referred to in that subclause within the period specified in that paragraph or within the time fixed by the arbitration award as aforesaid the State instead of determining this Agreement as aforesaid because of such default may itself remedy such default or cause the same to be remedied (for which purpose the State by agents workmen or otherwise shall have full power to enter upon lands occupied by the Company and to make use of all plant machinery equipment and installations thereon) and the actual costs and expenses incurred by the State in remedying or causing to be remedied such default shall be a debt payable by the Company to the State on demand.

Effect of cessation or determination of Agreement

Research tools for this sectionPro

The statute text is free to read above. View Pro plans to unlock the case-law research tools for each provision.

Section 23 — (1) In any of the following events namely if — — Dardanup Pine Log Sawmill Agreement Act 1992 (Western Australia) — Barrister AI