50
CurrentTerm of development approval
Part 10Dealing with applications for development approval
Division 2Determinations
50 Term of development approval
If development approval under this Scheme is granted —
(a)
the development of the land must be substantially commenced —
(i)
if no period is specified in the approval — within the period of 2 years commencing on the date of the determination; or
(ii)
if a period is specified in the approval — within that period; or
(iii)
in either case — within a longer period approved by the Commission on an application made under clause 55(1)(a);
and
(b)
the approval lapses if the development has not substantially commenced within the period determined under paragraph (a).
[Clause 50 inserted: Act No. 41 of 2024 s. 5.]