Revision because of a change, or proposed change, of circumstances or pipeline activity

In force

18 Revision because of a change, or proposed change, of circumstances or pipeline activity

(1)

The operator of a pipeline activity must submit to the Minister a proposed revision of the environment plan for the pipeline activity before the commencement of —

(a)

any new pipeline activity; or

(b)

any significant modification of, significant change in, or significant new stage of, an existing pipeline activity,

that is not provided for in the environment plan.

Penalty for this subregulation: a fine of $10 000.

(2)

The operator of a pipeline activity must submit to the Minister a proposed revision of the environment plan for the pipeline activity before or as soon as practicable after —

(a)

a change in the instrument holder for, or operator of, the pipeline activity; or

(b)

the occurrence of —

(i)

any significant new environmental impact or environmental risk; or

(ii)

any significant increase in an existing environmental impact or environmental risk,

that is not provided for in the environment plan for the pipeline activity; or

(c)

the occurrence of a series of new environmental impacts or environmental risks, or a series of increases in existing environmental impacts or environmental risks, which, taken together, amount to the occurrence of —

(i)

a significant new environmental impact or environmental risk; or

(ii)

a significant increase in an existing environmental impact or environmental risk,

that is not provided for in the environment plan for the pipeline activity.

Penalty for this subregulation: a fine of $10 000.

[Regulation 18 amended: SL 2026/82 r. 77.]