18A
CurrentPreloading works
Schedule 10Exempt development—Chapter 5
18A Preloading works
(1)
Preloading works for compression of soil before construction.
(2)
The development must—
(a)
disturb soil or vegetation only to the extent necessary to carry out the development, and
(b)
not damage any adjoining buildings or structures on the land or an adjoining lot, and
(c)
not redirect the flow of surface water onto an adjoining lot, and
(d)
not use fill other than—
(i)
virgin excavated natural material, or
(ii)
fill that is re-used in accordance with a resource recovery exemption in force under the Protection of the Environment Operations (Waste) Regulation 2014.