4.7
CurrentDevelopment in future infrastructure corridor for previously permitted uses of land
Chapter 4Future infrastructure corridors
4.7 Development in future infrastructure corridor for previously permitted uses of land
(1)
Despite section 4.6, development may be carried out with development consent on land within a future infrastructure corridor, but only if—
(a)
the development is of a kind that could be carried out on the land under an applicable environmental planning instrument immediately before the land was included within a future infrastructure corridor, and
(b)
where the proposed development has an estimated development cost of more than $200,000—Transport for NSW grants concurrence to the proposed development, and
(c)
the development is consistent with the aims of this Chapter.
(2) –(4)
(Repealed)