s 22A
In forceProject proponent must notify estimated completion date for a new relevant facility
Part 2Australian Industry Participation plans
Division 1Australian Industry Participation plans
22A Project proponent must notify estimated completion date for a new relevant facility
(1)
If:
(a)
the project proponent for a major project gives a draft AIP plan for the project to the Authority; and
(b)
the project involves establishing a new relevant facility; and
(c)
the establishment of the facility has not been completed;
the project proponent must:
(d)
notify the Authority of the estimated date of completion of the establishment of the facility; and
(e)
do so at or about the same time as the draft AIP plan is given to the Authority.
(2)
A notification under subsection (1) must be in a form approved, in writing, by the Authority.