Summary of approved site plan for public release
22 Summary of approved site plan for public release
Within 10 days after receiving notice under regulation 21(1) that the Minister has approved a draft site plan under regulation 18(1)(a), the applicant must submit to the Minister a summary of the approved site plan for public disclosure.
A summary submitted under subregulation (1) must include the following —
the name of the applicant;
the location or locations of the activity;
a general description of the existing subsurface conditions (baseline) that may be affected by the activity;
a summary of —
the construction and layout of any facility; and
the operational activity; and
any risks of the activity submitted as part of Schedule 2 clause 4; and
the detection and monitoring activities submitted as part of Schedule 2 clauses 5, 6, 7 and 8(2); and
the site closure activities submitted as part of Schedule 2 clause 8(1).
If the Minister is not reasonably satisfied that a summary submitted under subregulation (1) meets the criteria set out in subregulation (2), the Minister must give the applicant written notice that the applicant must modify and resubmit the summary.
Within 10 days after receiving a notice under subregulation (3) in relation to a summary of the approved site plan, the applicant must modify and resubmit the summary.