Before commencing building work
3 Before commencing building work
The following information must be provided no later than 2 business days before the commencement date of the building work—
the principal certifier’s name, registration number, class of registration held and email address,
the date the principal certifier was appointed as the principal certifier,
if the principal certifier is employed by a body corporate, the name of the body corporate, ABN or ACN and principal place of business,
if the principal certifier is employed by a council, the name and address of the council,
details of the building work,
the address of the land on which the building work is to occur,
the lot, deposited plan and section number of the land,
the local government area in which the land is located,
the total area of the land,
the name of the owner of the land,
the commencement date of the building work,
the total estimated cost of the building work,
the total floor area of buildings on the land before and after the building work will be completed,
if the building work involves the erection of 1 or more new buildings on the land, for each new building—
the total floor area of the building, and
the total number of storeys of the building, and
the total number of storeys below ground level, and
the classification of the building under the Building Code of Australia, and
whether the building will be used for residential purposes, non-residential purposes or a mixture of residential and non-residential purposes,
if any building on the land are, or will be, used for residential purposes—
the number of dwellings on the land before and after the building work will be completed, and
the number of dwellings to be demolished as part of the building work, and
the number of dwellings to be erected as part of the building work, and
whether the buildings are dwelling houses or dual occupancies,
if the building work includes a performance solution, any relevant section of the Building Code of Australia to which the performance solution relates,
if the building work is carried out under a development consent—
the development application number and the date on which development consent was granted, and
the details of the consent authority that granted consent including the name of the local government area, as applicable,
if the building work is carried out under a complying development certificate—
the number of the certificate and the date on which it was issued, and
the name and any ABN or ACN of the applicant for the certificate, and
if a council issued the certificate, the local government area of the council, and
if a registered certifier issued the certificate—
the name and registration number of the certifier, and
if applicable, the name, ABN or ACN and principal place of business of the certifier’s employer,
if the building work is subject to a construction certificate—
the construction certificate number and the date on which the certificate was issued, and
the name and any ABN or ACN of the applicant for the certificate, and
if a council issued the certificate, the local government area of the council, and
if a registered certifier issued the certificate—
the name and registration number of the certifier, and
if applicable, the name, ABN or ACN and principal place of business of the certifier’s employer.
In this clause—
dwelling, dwelling houses or dual occupancies have the same meaning as in the standard instrument set out in the Standard Instrument (Local Environmental Plans) Order 2006.