Modified procedure: notice requirements
52BD Modified procedure: notice requirements
An electrical contractor who decides to use the modified procedure in relation to notifiable work —
may advise the relevant network operator of their intention to use the procedure in the preliminary notice of proposed notifiable work delivered under regulation 52BB(4)(a) or the first such notice delivered under regulation 52BB(6)(a) (whichever is relevant); and
may decide to cease using the modified procedure in relation to any further notifiable work to be carried out as part of the construction project.
If an electrical contractor decides to cease using the modified procedure, the electrical contractor must give written notice to the relevant network operator of their intention to cease, on the day specified in the notice, using the modified procedure.
If an electrical contractor is required to cease using the modified procedure by order under regulation 52BC(4), the electrical contractor must give written notice to the relevant network operator of the requirement and the day specified in the order.
[Regulation 52BD inserted: Gazette 8 Jan 2019 p. 16.]