reg 14
In forcePart B requirements
14 Part B requirements
(1)
Part B of a draft site plan must —
(a)
be presented as “Part B — Other matters”; and
(b)
set out the information specified in Schedule 2; and
(c)
set out an integrated operations management plan showing clear chains of command where appropriate; and
(d)
include an appropriate strategy for the implementation of the site plan; and
(e)
include appropriate arrangements for monitoring, recording and reporting in relation to —
(i)
the implementation of the site plan; and
(ii)
compliance with the site plan.
(2)
Information set out in Part B of the draft site plan must be consistent with the declared identified GHG storage formation under section 69E of the Act.