(13) The State hereby grants the City a licence to enter onto the Padbury Building Land and to —
6 (13) The State hereby grants the City a licence to enter onto the Padbury Building Land and to —
demolish the buildings fences and other constructions on that land;
relocate any services on that land; and
implement that part of the Project which involves that land in accordance with the Timetable,
by its employees agents workmen licensees and contractors with any vehicles equipment plant and machinery as may be required to implement and complete the Project.
6. (14) The Minister for Railways and Westrail hereby grant the City a licence to enter onto the Westrail Land by its employees agents workmen licensees and contractors to enable the City to implement and complete that part of the Project which relates to the City Station Complex and the City shall ensure that persons entering onto the Westrail Land pursuant to this licence or authorised by the City to enter onto the Westrail Land pursuant to this licence comply with paragraph (c) of Item 7 of the Sixth Schedule and do not interfere with the operations of Westrail on the Westrail Land without Westrail’s prior approval.
6. (15) The licences granted pursuant to this Clause shall be irrevocable until they are no longer necessary for the purposes for which they are granted.
IMPLEMENTATION
7. (1) The City shall on or before the time specified in the Timetable invite tenders for and execute all building contracts and agreements necessary to implement and complete the Project.
7. (2) The City shall co‑ordinate and manage the Project on its own behalf and as agent for the State pursuant to Clause 5.
7. (3) The City shall, in implementing the Project, to the extent that is reasonable and economically practicable give preference to ratepayers of the City in letting contracts and purchasing materials and where that is not possible the City shall to that same extend —
use or ensure the use of the services of engineers, surveyors, architects and other professional consultants resident and available within Western Australia;
use or ensure the use of labour available within Western Australia; and
in respect of the preparation of specifications, calling for tenders and letting contracts for or in relation to the Project and materials, plant, equipment and supplies, ensure that Western Australian suppliers, manufacturers and contractors are given a fair and reasonable opportunity to tender or quote, and ensure proper consideration is given to Western Australian suppliers, manufacturers and contractors when letting contracts or placing orders for or in relation to the Project where price, quality, delivery and service are equal to or better than that obtainable elsewhere.
7. (4) Subject to Clause 16 the Parties shall do all things reasonably necessary to ensure that the Project is completed on or before 31 December 1987.
7. (5) The Parties shall use their best endeavours to comply with and permit the other Parties to comply with the Timetable and the Westrail Timetable.
7. (6) The City shall provide and maintain temporary pedestrian accessways during the implementation of the Project over such parts of the Reserved Land as may be required.
PROJECT COMMITTEE
8. (1) The Project Committee shall consist of the Minister, the Lord Mayor or the Deputy Lord Mayor of the City and the Chairman or Acting Chairman of the Metropolitan Region Planning Authority from time to time.
8. (2) The quorum for a meeting of the Project Committee shall be three and no member of the Project Committee may abstain from voting upon any matter referred to the Project Committee for its approval or decision.
8. (3) A resolution in writing signed or assented to by letter, telegram, or telex by each member of the Project Committee shall be as valid and effectual as if it had been passed at a meeting of the Project Committee.
8. (4) Westrail shall be entitled to make submissions to the Project Committee where the matter referred to the Project Committee affects railway property, Westrail’s operations on the Westrail Land, Westrail’s obligations and obligations to Westrail hereunder or Westrail’s contribution to the Project Costs and the Project Committee shall give due consideration to any such submission made by Westrail.
8. (5) Where any of the Parties is of the opinion that any of the other Parties has acted unreasonably or capriciously or where the Parties cannot agree upon any matter hereunder or agree any matter hereunder within the specified time or prior to the specified date, then any of the Parties may refer the matter to the Project Committee for its decision and the Parties agree to abide by its decision.
8. (6) The Project Committee shall promptly give its approval or make any decision as to the matter referred to it and the Parties agree to abide by any approval or decision of the Project Committee.
CITY STATION COMPLEX
9. (1) The City shall instruct the Architect in producing the Design Drawings to comply with the requirements set out in Item 6 of the Sixth Schedule and those requirements shall bind the Parties.