Temporary reliability standards for supply to Eastern Goldfields
13B Temporary reliability standards for supply to Eastern Goldfields
Electricity Networks Corporation must, so far as is reasonably practicable, have in place arrangements to—
restore and maintain at least 45MW of supply to essential services loads and the majority of small use customers in the Eastern Goldfields as soon as is reasonably practicable following the occurrence of an unplanned outage of a transmission element supplying the Eastern Goldfields; and
maintain at least 45MW of supply to essential services loads and the majority of small use customers in the Eastern Goldfields during the occurrence of a planned outage of a transmission element supplying the Eastern Goldfields.
[Section 13B inserted: Gazette 25 Sep 2018 p. 3568‑9.]