Floodplain harvesting—certification of inspections of water supply works
101 Floodplain harvesting—certification of inspections of water supply works
A duly qualified person who performs an inspection of a water supply work under Schedule 6, section 2(2) must give a certificate to the approval holder for the water supply work confirming if water entering the work—
is reasonably able to be measured by equipment that complies with the requirements of Schedule 5, or
is not able to be measured by equipment that complies with the requirements under Schedule 5.
A duly qualified person who performs an inspection of a water supply work under Schedule 6, section 2(3) must give a certificate to the approval holder for the water supply work confirming if the point-of-intake metering equipment for the water supply work—
is installed in compliance with the requirements of Schedule 5, or
is not installed in compliance with the requirements of Schedule 5.
The duly qualified person must give the certificate—
in the approved form and manner, and
within 7 days after the inspection.
Maximum penalty for subsection (3)—100 penalty units.
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.