In forceInformation by public utility provider to chief executive
323 Information by public utility provider to chief executive
(1)
If, in relation to public utility plant on busway land, a public utility provider does something mentioned in section 318(1), the provider must prepare records adequately defining the location of the plant.
(2)
A public utility provider owning public utility plant located on busway land must, if asked by the chief executive, give the chief executive information adequately defining the location of the plant.
Maximum penalty for subsection (2)—40 penalty units.