Baseline assessment plans for CMA tenures given, but not approved, before commencement
1318 Baseline assessment plans for CMA tenures given, but not approved, before commencement
This section applies if, before the commencement—
the holder of a CMA tenure had given the chief executive a baseline assessment plan for the area of the tenure; and
the chief executive had not approved the plan.
New chapter 3, part 3 applies in relation to the baseline assessment plan as if new section 396A(a) did not apply in relation to the CMA tenure.
Subsection (2) stops applying on the day an amendment of the underground water impact report for the cumulative management area takes effect under section 1315.
Note—See section 390 in relation to compliance by a resource tenure holder with an approved underground water impact report.
Also, if the chief executive approves the baseline assessment plan after the commencement, the holder of the CMA tenure must give the office a copy of the plan within 10 business days after being given notice of the chief executive’s decision to approve the plan.